Campus investments

Progress and timeline

  • July
    2012
    Contractors have been appointed for Phase 1 of the 1 West project and work is due to start on 20 August.
  • August
    2012
    • Planning applications for The Chancellors' Building, student accommodation and refectory and new Centre for the Arts have been submitted.
    • Planning permission for the 1 West expansion and refurbishment is granted.
  • Sept
    2012
    Planning permission for The Chancellors' Building is granted.
  • Oct
    2012
    The first phase of the 1 West enabling/demolition and asbestos removal works have now been completed and the main contractor, Cowlin Construction, is preparing to start the main extension works.
  • Feb
    2013
    Planning permission for the new student accommodation building is granted.
  • Mar
    2013
    Student accommodation building work started.
  • June
    2013
    • Planning permission for the new Centre for the Arts is granted.
    • The main construction work for the first phase of the 1 West Building refurbishments is completed.

Timeline

  • Sept
    2013
    Phase 1 of 1 West refurbishment due to open.
  • Oct
    2013
    The Chancellors' Building due to open.
  • Summer
    2014
    • Student accommodation and refectory due to open, subject to planning permission.
    • Centre for the Arts due to open, subject to planning permisson.
  • Sept
    2014
    Phase 2 of 1 West refurbishment due to open.
  • Sept
    2015
    Phase 3 of 1 West refurbishment due to open.

 

 

 